STT – CONSTRUCTION PHASING TIMELINE
STT – CONSTRUCTION PHASING TIMELINE 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 Mobilization & Fencing Works Mobilization & Site Setup Key Staff, equipment and sub-contractors will be mobilized. Temporary offices, welfare facilities, storage areas and laydown for construction team will be put in place before start of construction. Construction Fencing Works Construction Fencing will be erected ensuring clear demarcation of Construction & Operational Areas 3 Months (M0 to M3) Early Works Build Temp. Commuter Wing & Facilities in Existing Garage The hangar on the northern side of the terminal will be repurposed as a temporary commuter wing. In addition, temp. facilities will be constructed in the existing garage for relocation of departments, optimizing space and functionality during the construction phase. Moreover, early procurement of Long Lead Items shall start. …
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://dpnr.vi.gov/wp-content/uploads/2026/01/Proposed-Layout-and-Schedule.pdf
SHA-256 41e3fca8445e11bce6ce5b95eba04a1828b9383c79253f1e6577cb6ebc80738b
Re-using this document
A public record of the Government of the Virgin Islands, published by the agency itself. No copyright is asserted on it and 17 U.S.C. § 105 does not reach territorial government, so it publishes as a territorial public record.
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-41e3fca8445e
Document text
STT – CONSTRUCTION PHASING TIMELINE 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 Mobilization & Fencing Works Mobilization & Site Setup Key Staff, equipment and sub-contractors will be mobilized. Temporary offices, welfare facilities, storage areas and laydown for construction team will be put in place before start of construction. Construction Fencing Works Construction Fencing will be erected ensuring clear demarcation of Construction & Operational Areas 3 Months (M0 to M3) Early Works Build Temp. Commuter Wing & Facilities in Existing Garage The hangar on the northern side of the terminal will be repurposed as a temporary commuter wing. In addition, temp. facilities will be constructed in the existing garage for relocation of departments, optimizing space and functionality during the construction phase. Moreover, early procurement of Long Lead Items shall start. 4 Months Phase 1 New Commuter Wing Start construction of the new commuter wing building including foundations, structural elements, building envelope, architectural features, and MEP systems. Terminal Building – Level 2 & CUP Construction works in Level-2 of the terminal building and CUP including structural, architectural & MEP systems. Temp. Domestic Facilities Construction of the Temporary Domestic Facilities including required structural elements, building envelope, architectural features, and MEP systems. 20 Months (M4 to M23) New Aircraft Parking Plan & PAX Walkway Marking of aircraft parking spaces in accordance with temp layout plan, and PAX walkway to be constructed to implement parking plan and passenger flow. Ticket Counter & Department Relocation Relocation of Ticket Counters and Departments to temp. locations. 2.5 Months (M2 to M4) Phase 2 Terminal Building – Level 1 & Level 2 (Grid: D-N/10-18) Demolition and construction works in Level-1 & Level 2 of Terminal Building after relocation of Ticket Counter and Departments. 19 Months (M4 – M23) Phase 4 Removal of Temp. Domestic Facility & Reconfigure Commuter Wing to Final Layout Removal of Temp. Domestic Facility & Final configuration of the New Commuter Wing Building 5 Months (M44 to M48) Early Works Phase 1 Phase 2 Phase 3 Phase 3 Terminal Building – Level 1 & Level 2 (Grid F-T / 1-25) Demolition & construction works in existing structure, including foundation, structural, building envelope, architectural, and MEP works in the terminal building Level-1(Grid-5 to Grid-14) & Level-2. Continue construction works in Level-2 of the terminal building including structural, roofing, architectural & MEP systems. Testing & Commissioning of Equipment & MEP&T Systems Terminal Building – Baggage Arrival Area Construction works to existing structure, including foundation, structural, architectural, and MEP works will take place in the terminal building. CBIS/CBRA –BHS & Screening System – Level 1 Installation, Testing & Commissioning of CBIS/CBRA Area Screening Devices & BHS System International and TSA BHS & Screening System Installation, Testing & Commissioning of Screening & BHS System 20 Months (M24 – M43) ORAT Operational Readiness & Airport Transfer Training, Operational Trials, Passenger Stimulation & Handover to Airport Authority 30 Days (M44) Construction Start ORAT – Temp. Config. Operational Readiness & Airport Transfer Training, Operational Trials, Passenger Stimulation & Handover to Airport Authority 7 Days (M23) Phase 4 Final Inspection & Demobilization Final, Inspection, Rectification, Removal of North Airfield Operations & Garage Build-Out, Documentation and Demobilization. 3 Month (M49 to M51) Construction Complete 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 8/19/2025 Airport Overview & Project Area FIG. A-1 SCALE DATE Virgin Islands Port Authority COPYRIGHT SLR CONSULTING - 2025 ± 0 700 Feet 1:8,400 Cyril E. King Airport Reconstruction Project Legend Property Boundary Project Area Source: Maxar 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 8/19/2025 FIG. A-2 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 175 Feet 1:2,100 Permanent Demolition Existing Main Terminal Building to Remain Cooling Towers, Generator and Fuel Tanks New Commuter Wing Temporary Offices Temporary Laydown Areas Temporary Laydown Area & Offices/Sky City Office Chillers Internal (Second Floor) Temporary Commuter Wing further Northeast Temporary Domestic Facilities Temporary Baggage Legend Property Boundary Permanent Facilities Permanent Demolition Existing Main Terminal Chillers (Internal) Cooling Towers, Generator and Fuel Tanks New Commuter Wing Pavement Improvements Temporary Facilities Temporary Laydown Areas Temporary Offices Temporary Laydown and Office Temporary Baggage Temporary Domestic Facilities Temporary Commuter Wing Parking Area Temporary Commuter Wing Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community Total Construction Activities Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project Temporary Commuter Wing Apron Pavement Improvements Temporary Commuter Wing Parking Area Taxiway Pavement Improvements 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 9/18/2025 FIG. A-3 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 175 Feet 1:2,100 Permanent Demolition Existing Main Terminal Building Temporary Offices Temporary Laydown Areas Temporary Laydown Area & Offices/Sky City Office Temporary Commuter Wing further Northeast Existing Baggage Claim Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community, Maxar Construction Activities - Early Activities Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project Temporary Commuter Wing Apron Pavement Improvements Temporary Commuter Wing Parking Area Taxiway Pavement Improvements Temporary Commuter Wing Temporary Commuter Wing Parking Area Temporary Laydown and Office Temporary Offices Temporary Laydown Areas Temporary Facilities Pavement Improvements Existing Main Terminal Permanent Demolition Permanent Facilities Property Boundary Legend 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 8/19/2025 FIG. A-4 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 175 Feet 1:2,100 Existing Main Terminal Building to Remain Temporary Commuter Wing Temporary Commuter Wing Parking Area Approximate Distance 1500 ft Legend Property Boundary Permanent Facilities Existing Main Terminal Temporary Facilities Temporary Commuter Wing Parking Area Temporary Commuter Wing Maxar Construction Activities - Location of Temporary Commuter Wing Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 9/19/2025 FIG. A-5 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 60 Feet 1:760 Temporary Commuter Wing West half of existing hangar building to be repurposed as Temporary Commuter Wing. All construction associated with the temporary commuter wing is restricted to interior walls. Existing Hangar Building Estimated location of interior walls Temporary Commuter Wing Parking Area Apron Pavement Improvements Taxiway Pavement Improvements Taxiway F Source: USACE. Imagery from 2016-2017. Construction Activities - Temporary Commuter Wing Layout Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project Property Boundary Temporary Commuter Wing Hangar Space Temporary Commuter Wing Parking Area Legend Pavement Improvements 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 8/19/2025 FIG. A-6 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 175 Feet 1:2,100 Cooling Towers, Generator and Fuel Tanks New Commuter Wing Chillers Internal (Second Floor) Existing Main Terminal Building 1st & 2nd Floors Existing Baggage Claim Temporary Domestic Facilities Temporary Baggage New Aircraft Parking & Passenger Boarding Bridges New Aircraft Parking Temporary Domestic Facilities Temporary Baggage Temporary Facilities New Commuter Wing Cooling Towers, Generator and Fuel Tanks Chillers (Internal) Existing Main Terminal Permanent Facilities Property Boundary Legend Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community Construction Activities - Main Construction Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 9/18/2025 FIG. A-7 SCALE DATE COPYRIGHT SLR CONSULTING - 2025 ± 0 175 Feet 1:2,100 Cooling Towers, Generator and Fuel Tanks New Commuter Wing Temporary Offices Temporary Laydown Areas Temporary Laydown Area & Offices/Sky City Office Chillers Internal (Second Floor) Existing Main Terminal Building 1st & 2nd Floors Existing Baggage Claim Temporary Domestic Facilities Temporary Baggage New Aircraft Parking & Passenger Boarding Bridges X X X X X X Source: Source: Esri, Maxar, Earthstar Geographics, and the GIS User Community, Maxar Construction Activities - Decommission of Temporary Facilities Virgin Islands Port Authority Cyril E. King Airport Reconstruction Project Temporary Commuter Wing Apron Pavement Improvements Temporary Commuter Wing Parking Area Taxiway Pavement Improvements X X Temporary Commuter Wing Temporary Domestic Facilities Temporary Baggage Temporary Laydown and Office Temporary Office Temporary Laydown Areas Temporary Facilities New Commuter Wing Cooling Towers, Generator and Fuel Tanks Chillers (Internal) Existing Main Terminal Permanent Facilities New Aircraft Parking Property Boundary Legend XX Temporary Facility Removal Temporary Commuter Wing Parking Area Pavement Improvements 9/26/2025 241.031562.00002 8 East Broadway Suite 320 Salt Lake City, UT 84111 MXD: C:\USERS\CDICKES\ONEDRIVE - SLR CONSULTING LIMITED\SHAREPOINT PROJECT LINKS\NEPA\USVI AIRPORT REDEVELOPMENT\NEPA_ENVIRONMENTAL\GIS_ENV\03-MXDS\STT_FIGURES_ADDITIONAL_07_2025\STT_FIGURES_ADDITIONAL_07_2025.APRX DATE SAVED: 8/15/2025 Post-Construction Rendering FIG. A-8 SCALE DATE Virgin Islands Port Authority COPYRIGHT SLR CONSULTING - 2025 Cyril E. King Airport Reconstruction Project 9/26/2025 241.031562.00002