Tutu Well Fields Project Progress Report, July 1994
de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT JULY 1994 WORK COMPLETED DURING PREVIOUS MONTH • Continued preparation of Draft Rl Report. • Began preparation of Remedial Alternatives Analysis. • Participated in July 12, 1994 conference call between USEPA, TEIC, de maximis, inc. and Geraghty & Miller. • Groundwater samples were collected at the following supply well locations on the corresponding dates: Sampling Location Date Sampled VIHA I July 19, 1994 Four Winds II July 21, 1994 Four Winds I July 22, 1994 Delegarde July 27, 1994 (sampled for VOC analysis only) Harvey July 27, 1994 • Continued compilation and management of groundwater data. • Continued with data validation for groundwater sample results. WORK TO BE COMPLETED DURING NEXT MONTH • Complete surveying of storm sewer at Four Winds Plaza; Re-survey anomalous well elevations. • Complete data validation/data compilation for Comprehensive Groundwater Sampling Event. • Continue preparation of tables, figures, and text for Draft Rl Report. FILE 3O69 OAJULY PR TUT OO6 1O2O fMWI *64671* 64671
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://semspub.epa.gov/src/document/02/64671
SHA-256 472ffd665f5bd2379d3c818428c8aeb11ba3150ed98cae2fb79bc2a8730ff74f
Re-using this document
CERCLA administrative record
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-472ffd665f5b
Document text
de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT JULY 1994 WORK COMPLETED DURING PREVIOUS MONTH • Continued preparation of Draft Rl Report. • Began preparation of Remedial Alternatives Analysis. • Participated in July 12, 1994 conference call between USEPA, TEIC, de maximis, inc. and Geraghty & Miller. • Groundwater samples were collected at the following supply well locations on the corresponding dates: Sampling Location Date Sampled VIHA I July 19, 1994 Four Winds II July 21, 1994 Four Winds I July 22, 1994 Delegarde July 27, 1994 (sampled for VOC analysis only) Harvey July 27, 1994 • Continued compilation and management of groundwater data. • Continued with data validation for groundwater sample results. WORK TO BE COMPLETED DURING NEXT MONTH • Complete surveying of storm sewer at Four Winds Plaza; Re-survey anomalous well elevations. • Complete data validation/data compilation for Comprehensive Groundwater Sampling Event. • Continue preparation of tables, figures, and text for Draft Rl Report. FILE 3O69 OAJULY PR TUT OO6 1O2O fMWI *64671* 64671