Tutu Well Fields Project Progress Report, October 1994
de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT OCTOBER 1994 WORK COMPLETED DURING PREVIOUS MONTH • Submitted Draft Remedial Investigation (Rl) Report to USEPA and U.S. Virgin Islands Department of Planning & Natural Resources (DPNR) on October 13, 1994. After receiving confirmation from USEPA only limited distribution was made of Appendices K&L the validation documentation (including lab forms). This was sent to USEPA on October 13, 1994 under separate cover. • Submitted Development and Screening of Remedial Alternatives Analysis Report (RAA) to USEPA and DPNR on October 14, 1994. • Continued preparation of Draft Feasibility Study (FS) Report. WORK TO BE COMPLETED DURING NEXT MONTH • Attend meeting between Geraghty & Miller, TEIC, USEPA and the DPNR representatives from November 2, 1994 and November 3, 1994 in St. Thomas, U.S. Virgin Islands to present and discuss the Draft Rl Report and the RAA with the USEPA and DPNR. • Await formal comments on Draft Rl Report from USEPA and DPNR. • Await formal comments on RAA from USEPA and DPNR. …
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://semspub.epa.gov/src/document/02/64641
SHA-256 892ff8baca8db251eb3ba281d4c1c408165bb70954f7d03cf061fc22b2301ba8
Re-using this document
CERCLA administrative record
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-892ff8baca8d
Document text
de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT OCTOBER 1994 WORK COMPLETED DURING PREVIOUS MONTH • Submitted Draft Remedial Investigation (Rl) Report to USEPA and U.S. Virgin Islands Department of Planning & Natural Resources (DPNR) on October 13, 1994. After receiving confirmation from USEPA only limited distribution was made of Appendices K&L the validation documentation (including lab forms). This was sent to USEPA on October 13, 1994 under separate cover. • Submitted Development and Screening of Remedial Alternatives Analysis Report (RAA) to USEPA and DPNR on October 14, 1994. • Continued preparation of Draft Feasibility Study (FS) Report. WORK TO BE COMPLETED DURING NEXT MONTH • Attend meeting between Geraghty & Miller, TEIC, USEPA and the DPNR representatives from November 2, 1994 and November 3, 1994 in St. Thomas, U.S. Virgin Islands to present and discuss the Draft Rl Report and the RAA with the USEPA and DPNR. • Await formal comments on Draft Rl Report from USEPA and DPNR. • Await formal comments on RAA from USEPA and DPNR. • Prepare Final Rl Report addressing comments by USEPA and DPNR. The date of completion and submittal of the Final Rl Report is contingent upon receipt of formal comments from USEPA and DPNR. • Continue preparation of Draft FS Report. FILE: 3089.07\OCT.PR TUT 006 O653 MFC* *64641* 64641