Weekly Meeting Report - 9, Tutu Site Investigation, St. Thomas, U.S. Virgin Islands

Collection
Federal Reference
Sub-shelf
EPA SEMS (Superfund, Region 2)
Kind
Government Report
Island
St. Thomas
Date
1992-09-12
Pages
2
Text
Native Text

I SOIL TECH WEEKLY MEETING REPORT - 9 TUTU SITE INVESTIGATION ST. THOMAS, US VIRGIN ISLANDS PERIOD COVERED ATTENDING PREPARED BY DATE PREPARED August 31 to September 12, 1992 Ana Gloria Ramos, Designated Coordinator Clinton Moffatt, G&M Jose C. Agrelot, Soil Tech Jose C. Agrelot, Soil Tech Project Coordinator October 13, 1992 FIELD WORK COMPLETED FROM AUGUST 31 TO SEPTEMBER 12. 1992 o Monitoring wells MW-6 and MW-6R were completed during this period, o The removal and grouting of MW-6 was completed. o Drums containing soil cuttings are being relocated from borehole or monitoring well locations to a single storage area at the Kessler site. o Monitoring well development continued. o The data collected from the data logger installed at MW-9 was evaluated. Based on this data, a new shallow well was decided to be installed near MW-9. PROPOSED SCHEDULE FROM SEPTEMBER 13 TO SEPTEMBER 27. 1992 o Drilling and installation of MW-9S. o Continue with monitoring well development. o Coordination of the initial sampling round. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://semspub.epa.gov/src/document/02/64575

SHA-256 8a346e03767e6390b11006fd0a01b0a835a001aff69d9fb140272ed28065ad59

Re-using this document

CERCLA administrative record

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-8a346e03767e

Document text

I SOIL TECH WEEKLY MEETING REPORT - 9 TUTU SITE INVESTIGATION ST. THOMAS, US VIRGIN ISLANDS PERIOD COVERED ATTENDING PREPARED BY DATE PREPARED August 31 to September 12, 1992 Ana Gloria Ramos, Designated Coordinator Clinton Moffatt, G&M Jose C. Agrelot, Soil Tech Jose C. Agrelot, Soil Tech Project Coordinator October 13, 1992 FIELD WORK COMPLETED FROM AUGUST 31 TO SEPTEMBER 12. 1992 o Monitoring wells MW-6 and MW-6R were completed during this period, o The removal and grouting of MW-6 was completed. o Drums containing soil cuttings are being relocated from borehole or monitoring well locations to a single storage area at the Kessler site. o Monitoring well development continued. o The data collected from the data logger installed at MW-9 was evaluated. Based on this data, a new shallow well was decided to be installed near MW-9. PROPOSED SCHEDULE FROM SEPTEMBER 13 TO SEPTEMBER 27. 1992 o Drilling and installation of MW-9S. o Continue with monitoring well development. o Coordination of the initial sampling round. TUT OO6 O210 *64575* 64575 i SOI SOIL TECH_____ ——————————————— Weekly Meeting Report 9 Tutu Site Investigation St. Thomas, USV1 NEXT MEETING September 16, 1992 JCA/lvl/42614.wpf/92-1240 TUI OO6 O21.1