Text
Native Text

Disaster Recovery, Infrastructure & Planning – PSC Testimony PJ Platt – PSC Project Manager 1. Labor Recruitment Plan: • Our projects are scheduled to begin this year, ahead of many larger projects in the overall recovery pipeline. • This timing allows us to secure labor earlier, reducing competition for skilled trades. • We anticipate meeting most of our needs through existing contractor relationships and local subcontractors. 2. Source of Workforce: • We expect to rely primarily on local workforce and subcontractors given the scale and timing of our projects. • If supplemental labor is required, it will be targeted and limited, brought in only where specific skill gaps exist. 3. Worker Housing Plan: • Due to the smaller scale of our projects (approximately $12M range), our workforce size will be relatively modest. • We anticipate minimal housing demand, which can be accommodated through existing local housing and short-term rentals. • No large-scale or dedicated housing solutions are expected to be necessary. 4. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://legvi.org/committeemeetings/Disaster%20Recovery,%20Infrastructure%20and%20Planning/04%20-%20Apr.%2024,%202026/Block%20II/Contractors/PSC%20Testimony%20-%20Committee%20on%20Disaster%20Recovery,%20Infrastructure%20and%20Planning.pdf

SHA-256 8ffb1125f1612db7e827fdad6545258c021bce4cc5bf011590d0c5f22f5ace49

Re-using this document

A proceeding of the Legislature of the Virgin Islands, open to the public under 3 V.I.C. § 881, which reaches any committee of any branch of government and permits the news media to publish what it records.

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-8ffb1125f161

Document text

Disaster Recovery, Infrastructure & Planning – PSC Testimony PJ Platt – PSC Project Manager 1. Labor Recruitment Plan: • Our projects are scheduled to begin this year, ahead of many larger projects in the overall recovery pipeline. • This timing allows us to secure labor earlier, reducing competition for skilled trades. • We anticipate meeting most of our needs through existing contractor relationships and local subcontractors. 2. Source of Workforce: • We expect to rely primarily on local workforce and subcontractors given the scale and timing of our projects. • If supplemental labor is required, it will be targeted and limited, brought in only where specific skill gaps exist. 3. Worker Housing Plan: • Due to the smaller scale of our projects (approximately $12M range), our workforce size will be relatively modest. • We anticipate minimal housing demand, which can be accommodated through existing local housing and short-term rentals. • No large-scale or dedicated housing solutions are expected to be necessary. 4. Anticipated Challenges: • At this time, we do not foresee significant workforce or housing constraints. • Our early project start and smaller scale reduce exposure to: • Peak labor competition • Housing shortages driven by larger, billion-dollar projects • We will continue to monitor market conditions as additional projects come online. 5. Local Hiring Commitment • We are committed to prioritizing local hiring wherever feasible. • Our approach includes: • Partnering with local subcontractors and vendors • Utilizing the existing local labor pool first before seeking o:-island support • This approach helps support the local economy while also reducing logistical complexity. 6. Overall Positioning: As one of the first projects releasing within the bundle, we are uniquely positioned to: • Mobilize early • Avoid peak demand pressures • Our smaller project size vs. billion-dollar programs allows for a more manageable workforce footprint, minimizing strain on both labor and housing resources.