de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT NOVEMBER 1994 WORK COMPLETED DURING PREVIOUS MONTH • Meetings on November 2 and 3, 1994 were held in St. Thomas with USEPA, the U.S. Virgin Islands Department of Planning and Natural Resources (DPNR), Potentially Responsible Parties (PRPs), TEIC, and Geraghty & Miller representatives regarding the Draft Remedial Investigation (Rl) Report and Development and Screening of Remedial Alternatives Analysis (RAA). • On November 30th, de maximis, inc. on behalf of TEIC submitted a memorandum to EPA (Kwan) confirming revisions in the project schedule. That schedule is attached. WORK TO BE COMPLETED DURING NEXT MONTH • Await comments on Draft Rl Report from USEPA and DPNR (expected December 2, 1994). • Attend meeting with USEPA on December 15 at Region II offices regarding USEPA comments on Draft Rl Report. • Begin preparation of Final Rl Report addressing comments by USEPA and DPNR. • Continue preparation of Draft FS Report. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://semspub.epa.gov/src/document/02/64618

SHA-256 9493d4270608b51757708d968beb989cbf2b3dfd2128d1c1c85ea5c9c6c77abf

Re-using this document

CERCLA administrative record

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-9493d4270608

Document text

de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT NOVEMBER 1994 WORK COMPLETED DURING PREVIOUS MONTH • Meetings on November 2 and 3, 1994 were held in St. Thomas with USEPA, the U.S. Virgin Islands Department of Planning and Natural Resources (DPNR), Potentially Responsible Parties (PRPs), TEIC, and Geraghty & Miller representatives regarding the Draft Remedial Investigation (Rl) Report and Development and Screening of Remedial Alternatives Analysis (RAA). • On November 30th, de maximis, inc. on behalf of TEIC submitted a memorandum to EPA (Kwan) confirming revisions in the project schedule. That schedule is attached. WORK TO BE COMPLETED DURING NEXT MONTH • Await comments on Draft Rl Report from USEPA and DPNR (expected December 2, 1994). • Attend meeting with USEPA on December 15 at Region II offices regarding USEPA comments on Draft Rl Report. • Begin preparation of Final Rl Report addressing comments by USEPA and DPNR. • Continue preparation of Draft FS Report. FILE: 3089.07\NOV.PR TUT OO6 O53I *64618* 64618 de maximis Tutu Wells Site RI/FS Project Schedule Revised November 30, 1994 ERA Provides Soil and Groundwater Remedial Goals EPA Provides Final Comments On Rl Report and RATM To TEIC Meeting At EPA and with TEIC To Review Comments (NY City) TEIC Submits Draft Final RATM TEIC Submits Draft Final Rl Report TEIC Submits Draft FS Report To EPA EPA Hold Public Availability Meeting (St. Thomas) PRP Meeting To Discuss FS Report (St. Thomas) PRPs Submit Comments On FS To EPA EPA Provides Final Comments On FS To TEIC Meeting Between EPA And TEIC To Review FS Comments TEIC Submits Draft Final FS Report To EPA EPA Issues Proposed Remedial Action Plan (PRAP) Public Comment Period (Assume 30 day duration) EPA Public Meeting On PRAP EPA Signs ROD Special Notice Letters To PRPs Complete CD Negotiations With PRPs (Assume 120 days) Remedial Design Initiate Remedial Action (Construction) *EPA Comments on draft RATM to be incorporated into draft FS December 2, 1994 December 2, 1994 December 15, 1994 Deleted* January 30, 1995 February 13, 1995 March 14, 1995 March 15-16, 1995 March 27, 1995 April 7, 1995 April 20, 1995 May 17, 1995 June 6, 1995 June 6-July 6, 1995 Late June, 1995 July, 1995 August, 1995 December, 1995 Jan. 1996-Aug. 1996 September, FILJ SCHtOUU J» TUT 006 OS 32