Letter regarding Tutu Service Station Investigation Work Plan and Quality Assurance Project Plan, St. Thomas, U.S. Virgin Islands

Collection
Federal Reference
Sub-shelf
EPA SEMS (Superfund, Region 2)
Kind
Government Report
Island
St. Thomas
Date
1992-03-20
Pages
2
Text
Native Text

48TGERAGHTY 5S? MILLER, INC. Environmental Services Ground Water Engineering Hvdrocarbon Remedtfffwn Education March 20, 1992 Ms. Caroline Kwan, Project Manager U.S. Environmental Protection Agency New York, Caribbean Superfund Branch II 26 Federal Plaza New York, NY 10278 Re: Tutu Service Station Investigation Work Plan and Quality Assurance Project Plan, St. Thomas, U.S. Virgin Islands. Dear Ms. Kwan: On behalf of Ana Gloria Ramos, Designated Coordinator for the Tutu Environmental Investigation Committee (TEIC), Geraghty & Miller, Inc. is submitting four copies of the Work Plan and Quality Assurance Project Plan for the above referenced site. Please contact us if you have any questions or comments. Sincerely, GERAGHTY & MILLER, INC. Thomas V. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://semspub.epa.gov/src/document/02/64905

SHA-256 a5790efbb382a577c1339ae5706f57d7ce4f3be9584824db95394e3a41303088

Re-using this document

CERCLA administrative record

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-a5790efbb382

Document text

48TGERAGHTY 5S? MILLER, INC. Environmental Services Ground Water Engineering Hvdrocarbon Remedtfffwn Education March 20, 1992 Ms. Caroline Kwan, Project Manager U.S. Environmental Protection Agency New York, Caribbean Superfund Branch II 26 Federal Plaza New York, NY 10278 Re: Tutu Service Station Investigation Work Plan and Quality Assurance Project Plan, St. Thomas, U.S. Virgin Islands. Dear Ms. Kwan: On behalf of Ana Gloria Ramos, Designated Coordinator for the Tutu Environmental Investigation Committee (TEIC), Geraghty & Miller, Inc. is submitting four copies of the Work Plan and Quality Assurance Project Plan for the above referenced site. Please contact us if you have any questions or comments. Sincerely, GERAGHTY & MILLER, INC. Thomas V. Danahy Scientist/Project Manager Daniel Nachman Vice President/Project Officer TVD/DN/mtb PR01301-#2/032092.1tr TUT O06 1816 201 West Passaic Street, 3rd Floor• RocheUe Park, New Jersey 07662-(201) 909-0700-FAX (201) 909-0567/0568 *64905* 64905 cc: Ana Gloria Ramos, TEIC/Esso - 1 copy Jose Blanco, Esso - 1 copy Francis Torres, Goldman & Antonetti - 1 copy R. Scott McCay, Texaco - 1 copy Luiz Ruiz, Texaco Caribbean - 2 copies Jose Agrelot, Soil Tech - 2 copies Jose Font, USEPA Caribbean Field Office - 1 copy Laura Scalise, USEPA MMB - 1 copy Amy Chester, USEPA - 1 copy Leonard Reed, DPNR - 2 copies Sarah Odland, COM - 2 copies GERAGHTY & MILLER, INC. TUT °06 1S17