Phase II Remedial Investigation Implementation Schedule, Tutu Wells Site, St. Thomas, U.S. Virgin Islands
FIGURE 7-2 PHASE II REMEDIAL INVESTIGATION IMPLEMENTATION SCHEDULE GERAGHTY MILLER, INC. Environmental Services PR0013.001 AUTHORIZATION NO. TUTU WELLS SITE GERAGHTY & MILLER IMPLEMENTATION POTENTIALLY RESPONSIBLE PARTY REVIEW USEPA REVIEW MILESTONES LAB ANALYSIS PROJECT SCHEDULE SCH'D BY: D. NACHMAN DATE: 12-10-93 ST. THOMAS, U.S. VIRGIN ISLANDS CHK'D BY: T. DANAHY APPVD BY: D. NACHMAN DATE: 12-20-93 1993 1994 DEC I JAN FEE' MAR APR MAY JUNE JULY 10 26 1 I t« 23 30 6 13 M 27 « 13 20 27 3 10 17 24 1 > 15 22 M 5 12 It M 3 10 17 24 31 1995 JAN FEB MAR APR MAY JUNE I 1C 22 M 6 12 1* 28 B 12 It M 2 I It 23 30 7 14 21 4 11 II 26 PROPERTY ACCESS PROCUREMENT EARTH CHANGE PERMIT APPLICATION AND APPROVAL TASK 1 SITE INSPECTIONS 2 SITE INSPECTION REPORT 4 SOIL-GAS SURVEY REPORT 5 MONITORING WELL AND SUPPLY WELL SURVEYING 6 SUPPLY WELL INSPECTION 7 PUMPAGE IMPACT MONITORING _ MONITORING WELL INSTALLATION AND 8 STORM SEWFR INVFSTIGATIQN 9 WATER-LEVEL MEASUREMENTS 10 COMPREHENSIVE GROUNDWATER SAMPLING EVENT 12 MONTHLY REPORTS 15 ANALYSIS OF REMEDIAL ALTERNATIVES 16 DRAFT FEASIBILITY STUDY B:TU-26 …
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://semspub.epa.gov/src/document/02/64547
SHA-256 af9a8fb83ab1745a8003850d244907d4ae41e844a751c99101e9ffd0b1b4660c
Re-using this document
CERCLA administrative record
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-af9a8fb83ab1
Document text
FIGURE 7-2 PHASE II REMEDIAL INVESTIGATION IMPLEMENTATION SCHEDULE GERAGHTY MILLER, INC. Environmental Services PR0013.001 AUTHORIZATION NO. TUTU WELLS SITE GERAGHTY & MILLER IMPLEMENTATION POTENTIALLY RESPONSIBLE PARTY REVIEW USEPA REVIEW MILESTONES LAB ANALYSIS PROJECT SCHEDULE SCH'D BY: D. NACHMAN DATE: 12-10-93 ST. THOMAS, U.S. VIRGIN ISLANDS CHK'D BY: T. DANAHY APPVD BY: D. NACHMAN DATE: 12-20-93 1993 1994 DEC I JAN FEE' MAR APR MAY JUNE JULY 10 26 1 I t« 23 30 6 13 M 27 « 13 20 27 3 10 17 24 1 > 15 22 M 5 12 It M 3 10 17 24 31 1995 JAN FEB MAR APR MAY JUNE I 1C 22 M 6 12 1* 28 B 12 It M 2 I It 23 30 7 14 21 4 11 II 26 PROPERTY ACCESS PROCUREMENT EARTH CHANGE PERMIT APPLICATION AND APPROVAL TASK 1 SITE INSPECTIONS 2 SITE INSPECTION REPORT 4 SOIL-GAS SURVEY REPORT 5 MONITORING WELL AND SUPPLY WELL SURVEYING 6 SUPPLY WELL INSPECTION 7 PUMPAGE IMPACT MONITORING _ MONITORING WELL INSTALLATION AND 8 STORM SEWFR INVFSTIGATIQN 9 WATER-LEVEL MEASUREMENTS 10 COMPREHENSIVE GROUNDWATER SAMPLING EVENT 12 MONTHLY REPORTS 15 ANALYSIS OF REMEDIAL ALTERNATIVES 16 DRAFT FEASIBILITY STUDY B:TU-266 TUT 005 O26'.: *64547* 64547