Virgin Islands Government, Department of Public Works, FEMA Disaster No. 1067-DR-VI, Audit Report No. DA-24-03
ENT OF HOMELAND SECURI Office of Inspector General Atlanta Field Office-Audit Division 3003 Chamblee Tucker Rd Atlanta, GA 30341 August 27,2003 MEMORANDUM TO: Joseph F. Picciano Acting Regional~ctor, FEMA Region I1 FROM: Field Office Director SUBJECT: Virgin Islands Government, Department of Public Works FEMA Disaster No. 1067-DR-VI Audit Report No. DA-24-03 The Office of Inspector General (OIG) audited public assistance funds awarded to the Virgin Islands (V.I.) Department of Public Works (DPW). The objective of the audit was to determine whether DPW and other V.I. Government entities accounted for and expended FEMA h d s according to federal regulations and FEMA guidelines. The DPW received an award of $1 1.4 million kom the V.I. Office of Management and Budget (OMB), a FEMA grantee, for debris removal, emergency protective measures and repairs to roads and other facilities damaged as a result of Hurricane Marilyn in September 1995. The award provided 90 percent FEMA funding for 32 large projects and 87 small projects.' The audit covered the period September 1995 to January 2001. …
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://archive.org/download/240657-virgin-islands-government-department-of-public/240657-virgin-islands-government-department-of-public.pdf
SHA-256 c12b67ed6b7d84573d765b3e7d9f4b7c9c38cfe263dc1b127d61ac12c1f6bc85
Re-using this document
mixed and recorded per item: public domain by age or as a US government work for what was taken; controlled-digital-lending and restrictively licensed items EXCLUDED, each listed with its reason
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-c12b67ed6b7d
Document text
ENT OF HOMELAND SECURI Office of Inspector General Atlanta Field Office-Audit Division 3003 Chamblee Tucker Rd Atlanta, GA 30341 August 27,2003 MEMORANDUM TO: Joseph F. Picciano Acting Regional~ctor, FEMA Region I1 FROM: Field Office Director SUBJECT: Virgin Islands Government, Department of Public Works FEMA Disaster No. 1067-DR-VI Audit Report No. DA-24-03 The Office of Inspector General (OIG) audited public assistance funds awarded to the Virgin Islands (V.I.) Department of Public Works (DPW). The objective of the audit was to determine whether DPW and other V.I. Government entities accounted for and expended FEMA h d s according to federal regulations and FEMA guidelines. The DPW received an award of $1 1.4 million kom the V.I. Office of Management and Budget (OMB), a FEMA grantee, for debris removal, emergency protective measures and repairs to roads and other facilities damaged as a result of Hurricane Marilyn in September 1995. The award provided 90 percent FEMA funding for 32 large projects and 87 small projects.' The audit covered the period September 1995 to January 2001. During this period, the V.I. Government claimed $10,415,545 (see Exhibit) and received $9,151,720 of F E W funds. The OIG performed the audit under the authority of the Inspector General Act of 1978, as amended, and according to generally accepted government auditing standards. The audit included tests of the V.I. Government's accounting records, a judgmental sample of expenditures, and other auditing procedures considered necessary under the circumstances. I According tQFEMA regulations, a large project cost $43,600 or more and a small project cost less than $43,600. RESULTS OF AUDIT The V.I. Government did not maintain accurate records on the receipt of program funds and did not always follow sound contracting procedures for awarding contracts for project activities. Also, DPW claimed questioned costs of $772,881 (FEMA share - $695,593) resulting from charges that were unsupported, unrelated to the FEMA projects, or duplicative in nature. A. Grant Accounting. Federal regulation (44 CFR 13.20) requires subgrantees to maintain accurate, current, and complete accounting records on federal grant programs. However, the V.I. Government's records on the receipt of funds for DPW were understated by $1,8 15,650 due to accounting errors and a lack of reconciliation. The V.I. Department of Finance was responsible for maintaining the official accounting records of the V.I. Government and accounting for the receipt and expenditure of all federal grant funds. To account for FEMA h d s under Disaster 1067, the Department of Finance established a separate DPW cost center for receipt and expenditure. The OMB, on the other hand, was responsible for withdrawing FEMA program funds from the U.S. Treasury and reporting such withdrawals to the Department of Finance. Additionally, both OMB and Department of Finance were responsible for coordinating their efforts and reconciling their accounts. The OIG determined that this was not done and the Department of Finance failed to maintain accurate records on the receipt of funds for the DPW. OMB records showed that the V.I. Government requested and received $9,151,720 under Disaster 1067 for DPW. OMB submitted reports to the Department of Finance confirming ths amount. However, the Department of Finance records reflected only $7,336,070, or $1,815,650 less than the amount in OMB records. The OIG determined that the Department of Finance incorrectly posted $3,965,080 of DPW funds to accounts established for the Department of Education ($3,746,268); Internal Revenue Bureau ($42,635); and other entities ($176,177). Also, $2,149,430 of receipts posted to DPW's FEMA account should have been posted to other DPW accounts, or the accounts of other V.I. Government entities. B. Contracting Practices. Federal regulation (44 CFR 13.36) requires subgrantees to maintain records sufficient to detail the significant history of procurements, including the rationale for the method for such procurements and the basis for the contractor selection and contract price. However, DPW did not comply with these requirements, as illustrated by Finding C, and failed to exercise sound contracting and cost control practices. Specifically, DPW did not document the basis for contractor selection and contract price. Additionally, DPW 4 - entered into several verbal contracts for debris removal work valued at $6.7 million without subsequently documenting the contract terms and conditions. C. Unsuv~orted Charges. Federal regulation (44 CFR 13.20)requires subgrantees to maintain supporting documentation for all charges to FEMA projects. However, DPW's claim included $678,481 of contract charges that were not supported by adequate documentation. 1. Three contractors billed DPW $397,350 for debris removal activities on St. Thomas and St. John. Each contractor submitted invoices reporting work performed at various sectors of the islands. However, written contracts were not available to identify the scope of work or the basis for compensation. Additionally, DPW did not have any records reflecting the amount of debris collected, equipment used,identity of the equipment operators, or number of hours worked on the FEMA projects. As a result, the OIG questions the appropriateness of these charges. The affected projects are: Amount Proiect No. Questioned Location Sector 22493 $180,000 St. Thomas Zone B1 22486 1 12,000 St. Thomas Zone B1 and B2 62204 105.350 St. John Routes 102,103,107 108,109 Total 2. DPW hired two contractors under Project 56396 to install roof tarps on damaged homes located on St. Thomas. Both contractors submitted invoices identifjnng the homes where tarps were installed and the amount of material used on each home. However, one of the contractors billed and received compensation of $587,694 for 786,756 square feet, mitted support for the installation of only feet. Therefore, the 344,641 square feet v $258,062. ($.7488 per square foot X 344,641). 3. DPW claimed a total $608,956 for work done under several projects. However, transactions in the of Finance's official accounting records reflected costs of $585,887. questions the unsupported charges of $23,06 as follows: Amount Amount Amount DSR Claimed Supported Unsupported 22506 $181,707 $176,227 $ 5,480 5 826 1 381,760 364,SO 1 17,259 22526 45.489 45.159 330 %608.956 li2lLEu %23.069 D. Unrelated Project Charges. DPW's claim under two projects included $59,276 of unrelated project charges. Project 72568 provided for repairs to an access roadat the airport lagoon on St. Thomas. However, the claim of $63,118 under this project included $42,000 to remove sludge fiom a wastewater treatment plant at the lagoon. These charges were unauthorized and did not benefit the project. Also, the DPW's claim of $175,953 under Project 55853 included $17,276 of labor and equipment costs that were incurred two weeks, to a month, before the disaster. Accordingly, these costs did not benefit and were unrelated to the debris removal project. Federal regulation (U.S. OMB circular A-87, C.1.a) requires that for cost to be allowable under a federal grant program, it must be necessary and reasonable for proper and efficient administration of the program. Accordingly, the OIG questions the $59,276 of unrelated project charges. E. Duplicate Charges. Federal regulation (44 CFR 206.191) prohibits duplication of benefits between FEMA programs and those of other federal agencies. However, DPW's claim included $35,124 of charges that were h d e d by other sources or were duplicate in nature. 1. DPW received $5,444 under small Project 2291 1 for the disposal of two house trailers on St. Croix. However, DPW also claimed and received $5,000 for disposal of the same two trailers under large Project 9321 1. Therefore, the OIG questions DPW claim of $5,444 under Project 2291 1. 2. DPW claimed $9,719 under Project 55802 for erosion repairs at Long Bay on St. Thomas. However, DPW also received funds from the Federal Highway Administration to cover the same activity. Accordingly, the OIG questions $9,719 of duplicate funding. DPW9S claim under Project 56896, awarded for the purpose of installing tarps on damaged homes, contained $19,96 1 of duplicate charges. The Department hired two contractors' to perform these activities and paid $1,530,476 based on contractors' billing. However, the contracts did not specify the areas covered by the two contractors and the 016 found the contractors bills identified tarp installation to the same 15 homes. One contractor claimed $18,530 for tarp installation on the 15 homes during December 1995 to January 19, 1996. The other claimed $19,961 during January 23, 1996 to July 10, 1996. Therefore, the OIG questions the duplicate claim of $19,961. RECOMMENDATIONS The OIG recommends that the Regional Director, in coordination with the OMB: 1. Instruct the Department of Finance to coordinate their accounting efforts with the OMB and ensure that records on the receipts of federal h d s are timely and appropriately reconciled; 2. Instruct the Department of Public Works to comply with applicable procurement requirements when implementing FEMA projects in the future; and 3. Disallow the $772,881 of questioned costs. The OIG discussed the results of the audit with FEMA, OMB and the DPW officials on June 12, 2003. DPW officials generally concurred with the findings but indicated that an attempt to support questioned costs. Please advise the Atlanta Field Office-Audit Division by September 29, 2003, of actions taken to implement our recommendations. Should you have questions concerning this report, please contact me at (770) 220-5242. EXHIBIT V.I.Govemnt. Department of Public Works FEMA Disaster No. 1067-DR-VI Schedule of Claimed and Questioned Costs Large Proiects Project Amount Amount Amount Number Awarded Claimed Questioned 22486 $ 112,900 $ 112,000 $1 12,000 Finding C 22487 62,500 62,500 0 22488 100,000 100,000 0 22489 97,482 97,482 0 22490 97,000 97,000 0 22491 96,500 96,500 0 22492 52,000 52,000 0 22493 18O,OOO 180,000 180,000 Finding C 22494 50,000 50,000 0 22505 1,38 1,478 1,307,853 0 55853 195,503 175,953 17,276 Finding D 58261 336,760 381,760 17,259 Finding C 58734 294,934 294,934 0 62204 1,095,527 812,762 105,350 Finding C 77676 1,420,320 1,360,320 0 93211 1,921,575 1,911,736 0 93287 316,712 306,570 0 58560 418,139 418,139 0 22506 195,733 18 1,707 5,480 Finding C 55844 45,556 45,556 0 22203 44,869 0 0 93209 51,757 0 0 37086 5 1,900 0 0 37379 44,229 0 0 56896 1,530,856 1,530,096 258,062 Finding C 56896 19,961 Finding E 56897 232,750 0 57 192 77,603 0 72568 63,118 42,000 Finding D 22526 48,992 330 Finding C 55847 128,478 0 57019 45,199 0 58736 61,361 0 Sub-totals $10,851,731 $757,718 Small Proiects 55802 9,719 Finding E 2291 1 5,444 Finding E All other small project 580.371 Sub-total $ 595,534 Totals