de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT MAY 1994 WORK COMPLETED DURING PREVIOUS MONTH • Completion of the following Phase II drilling activities: Installation of Monitoring Wells MW-20, MW-20D, and MW-24. Completion of well development, including Monitoring Wells MW-13D, MW-22D, MW-20, MW-20D, and MW-24. Repair of 4-inch polyvinyl chloride (PVC) cistern pipe near Monitoring Well MW-24. • Water-level measurements taken of supply wells and monitoring wells during the week of May 9, 1994. • Ground water sampling of supply wells and monitoring wells commenced during the week of May 18, 1994. • Laboratory coordination including bottle ordering, shipments, and letters to U.S. Environmental Protection Agency (USEPA) regarding sampling procedures. • Site access Revisions. • Pumpage impact monitoring of Eglin III supply well. The following work was performed: Installation of water meter at Eglin III. Procurement of materials and equipment. Water-level measurements in observation wells. Trucked water provided to well owner during pumping test. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://semspub.epa.gov/src/document/02/64692

SHA-256 d2953d9f6836c6edd3ae452b0a6e4a954249e95e8c127f9c3beed11268c7a513

Re-using this document

CERCLA administrative record

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-d2953d9f6836

Document text

de maximis TUTU WELL FIELDS PROJECT PROGRESS REPORT MAY 1994 WORK COMPLETED DURING PREVIOUS MONTH • Completion of the following Phase II drilling activities: Installation of Monitoring Wells MW-20, MW-20D, and MW-24. Completion of well development, including Monitoring Wells MW-13D, MW-22D, MW-20, MW-20D, and MW-24. Repair of 4-inch polyvinyl chloride (PVC) cistern pipe near Monitoring Well MW-24. • Water-level measurements taken of supply wells and monitoring wells during the week of May 9, 1994. • Ground water sampling of supply wells and monitoring wells commenced during the week of May 18, 1994. • Laboratory coordination including bottle ordering, shipments, and letters to U.S. Environmental Protection Agency (USEPA) regarding sampling procedures. • Site access Revisions. • Pumpage impact monitoring of Eglin III supply well. The following work was performed: Installation of water meter at Eglin III. Procurement of materials and equipment. Water-level measurements in observation wells. Trucked water provided to well owner during pumping test. • Surveying of newly installed monitoring wells. TUT OO6 1C) 4 8 *64692* 64692 de maximis TuTu Progress Report June 10, 1994 WORK TO BE COMPLETED DURING NEXT MONTH • Completion of monitoring well sampling (expected to finish June 17). • Begin preparation of the Draft Rl report including: Soil quality data validation. Pumping impact data analysis. Preparation of geologic and well construction logs for new monitoring wells. Base map revisions based on surveying. Preparation of groundwater contour maps. TUT OO6 1049 o