A VI Update Project · Brian LoudenThe territory’s public record — kept public.

Letter regarding attached Tutu Well Site, Administrative Order on Consent, Index No. II-RCRA-Proceeding 7003 and 9003-92-0401 Monthly Progress Report No. 18

Collection
Federal Reference
Sub-shelf
EPA SEMS (Superfund, Region 2)
Kind
Government Report
Date
1993-08-13
Pages
2
Text
Native Text

Ana Gloria Ramos, P.E. Designated Coordinator Tutu Environmental Investigation Committee (T E I C) G.P.O. Box 4269 San Juan, Puerto Rico 00936-4269 August 13, 1993 Eng. Caroline Kwan Project Manager New York/Caribbean Super fund Branch II Emergency and Remedial Response Division US Environmental Protection Agency Region II 26 Federal Plaza New York, New York 10278 RE: Tutu Well Site Administrative Order on Consent Index No. II-RCRA-Proceeding 7003 and 9003-92-0401 Monthly Progress Report No. 18 Dear Mrs . Kwan : Attached find the Written Monthly Progress Report for the subject Administrative Order. If you have any question regarding this matter, please contact the undersigned at (809) 749-8943. Very truly yours, Ana Gloria Ramos, P.E. Designated Coordinator AGR/mpt/EPAKWAN Attachments pc: Mr. J. Juanet Mr. D. Lee Scott McCay, Esq. - Texaco Mr. L. Ruiz - Texaco Jose A. Cepeda/Francis Torres, Esqs. Mr. Jose Font - EPA Caribbean Field Office Mr. Roy E. Adams - Commissioner DPNR-USVI Mr. Leonard Reed/ Mr. Benjamin Nazario - DPNR-USVI Mr. J. C. Agrelot - Soil Tech Mr. T. …

Download the original document · Plain text (TXT) · Browse the archive · How this archive works

Original source: https://semspub.epa.gov/src/document/02/64766

SHA-256 d99049eff1f7db46b5f50f058bc251981f5d185251ba4a62a92baa45e136c018

Re-using this document

CERCLA administrative record

Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.

Archive identifier LF-d99049eff1f7

Document text

Ana Gloria Ramos, P.E. Designated Coordinator Tutu Environmental Investigation Committee (T E I C) G.P.O. Box 4269 San Juan, Puerto Rico 00936-4269 August 13, 1993 Eng. Caroline Kwan Project Manager New York/Caribbean Super fund Branch II Emergency and Remedial Response Division US Environmental Protection Agency Region II 26 Federal Plaza New York, New York 10278 RE: Tutu Well Site Administrative Order on Consent Index No. II-RCRA-Proceeding 7003 and 9003-92-0401 Monthly Progress Report No. 18 Dear Mrs . Kwan : Attached find the Written Monthly Progress Report for the subject Administrative Order. If you have any question regarding this matter, please contact the undersigned at (809) 749-8943. Very truly yours, Ana Gloria Ramos, P.E. Designated Coordinator AGR/mpt/EPAKWAN Attachments pc: Mr. J. Juanet Mr. D. Lee Scott McCay, Esq. - Texaco Mr. L. Ruiz - Texaco Jose A. Cepeda/Francis Torres, Esqs. Mr. Jose Font - EPA Caribbean Field Office Mr. Roy E. Adams - Commissioner DPNR-USVI Mr. Leonard Reed/ Mr. Benjamin Nazario - DPNR-USVI Mr. J. C. Agrelot - Soil Tech Mr. T. Danahy - Geraghty & Miller Andrew Prashak, Esq. - USEPA Caribbean Field Office TUT OO<b .1378 Telephone: (809) 792-2920 Fax. (809) 793-6555 *64766* 64766 MONTHLY PROGRESS REPORT NO. 18 August 13, 1993 RE: Administrative Order on Consent Index No. II - RCRA - Proceeding 7003 & 9003-92-0401 This status report includes the work performed during the period from July 1 through July 31, 1993. WORK COMPLETED DURING PREVIOUS MONTH Continued data analysis and preparation of the RI Report . Continued working with Ramsay and Four Winds representatives to get access agreements at these properties for installation of proposed monitoring wells. Prepared a draft cost estimate for remaining work of RI/FS. Reviewed previous work conducted by Geocim (O1 Henry Consultant) in the vicinity of 0' Henry Dry Cleaning. Began coordinating format for transfer of chemical data electronically to U.S. Environmental Protection Agency's (USEPA) subcontractor, CDM Federal Programs for risk assessment. WORK TO BE COMPLETED DURING NEXT MONTH Continue data analysis and preparation of the RI Report. Continue working with Ramsay and Four Winds representatives to get access agreements at these properties for installation of proposed monitoring wells. Continue preparations for mobilization. Complete data transfer to CDM Federal Programs for risk assessment. ANA GLORIA RAMOS TUT OO6 .1379