GERAGHTY '& MILLER. INC. Environmental Services July 6. 1994 Leonard Reed Department of Planning & Natural Resources Nisky Center 8000, Suite 45 St. Thomas, USVI 00802 Re: Groundwater Monitoring, Tutu Wells Site Remedial Investigation. Dear Mr. Reed: On behalf of the Tutu Environmental Investigation Committee (TEIC) and as part of the Remedial Investigation (RI) groundwater monitoring task, Geraghtv & Miller, Inc. is proposing to remove the existing submersible pump and repair the well head at the Harvey well. The well could not be sampled during the Phase II of the RI because the submersible pump was not working. In order to get access to purge the well and collect the sample, the existing submersible pump and piping will have to be removed from the well. The scope of work will consist of the removal of piping and submersible pump from the well with a small pump truck, and repair of the steel casing at the well head. Field activities will be performed by a local contractor. Poly Caribe, under Geraghty & Miller supervision. TUT 006 1042 809 Fernandez Juncos Avenue• Sanmrce. …
Download the original document · Plain text (TXT) · Browse the archive · How this archive works
Original source: https://semspub.epa.gov/src/document/02/64689
SHA-256 e432d33db0abe99b947d8720e07685c993f3b74cec0e6fd2d946121911ff77a5
Re-using this document
CERCLA administrative record
Our description, tagging, arrangement, extracted text and machine transcripts are released under CC0 1.0. We assert nothing about the document itself.
Archive identifier LF-e432d33db0ab
Document text
GERAGHTY '& MILLER. INC. Environmental Services July 6. 1994 Leonard Reed Department of Planning & Natural Resources Nisky Center 8000, Suite 45 St. Thomas, USVI 00802 Re: Groundwater Monitoring, Tutu Wells Site Remedial Investigation. Dear Mr. Reed: On behalf of the Tutu Environmental Investigation Committee (TEIC) and as part of the Remedial Investigation (RI) groundwater monitoring task, Geraghtv & Miller, Inc. is proposing to remove the existing submersible pump and repair the well head at the Harvey well. The well could not be sampled during the Phase II of the RI because the submersible pump was not working. In order to get access to purge the well and collect the sample, the existing submersible pump and piping will have to be removed from the well. The scope of work will consist of the removal of piping and submersible pump from the well with a small pump truck, and repair of the steel casing at the well head. Field activities will be performed by a local contractor. Poly Caribe, under Geraghty & Miller supervision. TUT 006 1042 809 Fernandez Juncos Avenue• Sanmrce. Puerto Rico 00907-(809) 725-2304-FAX (809) 725-2344 *64689* 64689 Geraghty & Miller would like to request your assistance in obtaining the approval of the well owner, Ms. Inez Harvey, to proceed with these activities. Please contact us if you have any questions. Thank you for your cooperation in this matter. Sincerely, GERAGHTY & MILLER, INC. CC: Geoffrey Seibel, de maximis inc. Caroline Kwan, USEPA Wanda I. Morales Staff Scientist t- Thomas V. Danahy /Senior Scientist/Project Manager " - Daniel A. Nachman President/Project Officer TUT O06 1O43 GERAGHTY c> MILLER. !\:C. ^GERAGHTY '& MILLER. INC. Environmental Services July 6, 1994 Ralda V. Simmonds, Esq. Virgin Islands Housing Authority 402 Annes Street P.O. Box 7668 St. Thomas, USVI 00801 Re: Groundwater Monitoring, Tutu Wells Site Remedial Investigation. Dear Ms. Simmonds: On behalf of the Tutu Environmental Investigation Committee (TEIC) and as part of the Remedial Investigation (RI) groundwater monitoring wells sampling task, Geraghty & Miller, Inc. is proposing the removal of the existing submersible pump from supply well VIHA I. The well was not sampled during the implementation of the Phase II of the RI because the submersible pump was not working. In order to get access to purge the well and collect the sample, the existing submersible pump and piping will have to be removed from the well. The scope of work will consist of the removal of existing pipe and the submersible pump with a small pump truck, purging the well with a submersible pump, and collecting the water sample with a teflon bailer after completion of purging. Work will be performed by a local contractor. Poly Caribe, under Geraghty & Miller supervision. The field work will require approximately two days (one day to remove the pump and piping; one day to purge and sample TUT OO6 1O44 809 Fernandcz Juncos Avenue • Santurce. Puerto Rico 00907 -(809) 725-2304 -FAX (809) 725-2344 the well), depending on the conditions of the pipe and submersible pump. Please contact us if you have any questions. Thank you for your cooperation in this matter. Sincerely, GERAGHTY & MILLER. INC. CC: Geoffrey Seibel, de maximis inc. Caroline Kwan, USEPA Wanda I. Morales Staff Scientist Thomas V. Danahj ^Senior Scientist/Project Manager , lyoj^jjL^H . — Daniel A. Nachman Vice President/Project Officer '5ERAGHTY ~ MILLER. INC. TUT °°6 1O45